The sixth month of work on the construction of the tram route to Mistrzejowice is behind us. In December, we continued the construction of the “Polsadu Roundabout” station and the new channel of the Sudół Dominikański watercourse. What else kept us busy?
In December, exceptionally due to the holiday period, we held only one Construction Council with the participation of the public. At the meeting, residents were able to learn about the changes in the Lublańska Street design and talk to representatives of the Private Partner and Local Government Entities about issues of interest to them.
On December 11, we opened the Information Center. Kraków residents can obtain information on, among other things, construction technology, the progress of works or traffic organization. It is located near the intersection of Dobrego Pasterza and Strzelców streets and is open on weekdays from 8:00 a.m. to 4:00 p.m. Feel free to drop by! More.
On December 12, we met with representatives of the City of Kraków to present the current progress of our works. We discussed various aspects of the project, in particular the reconstruction of the multi-kilometer underground infrastructure.
Throughout the month, our work focused on the construction of the tunnel for the tram route to Mistrzejowice; particularly on the construction of the “Polsadu Roundabout” station and the new channel of the Sudół Dominikański.
We have also started work on the Młyńskie Roundabout, including construction:
- execution of preliminary excavations and working platforms for the construction of the diaphragm walls of the “Rondo Młyńskie” station and the turnout chamber of the next stage of KST,
- working platforms for the construction of station exits,
- relocation of utility networks colliding with the construction of the tunnel structure.
What’s in store for January?
Starting January 11, some modifications will be made to the current temporary traffic organization. These changes will include a section of Lublańska Street and Bora-Komorowskiego Avenue. More.
In January, our deep-worker, known as “Lucjan”, will continue work related to the sinking of diaphragm walls for the “Rondo Polsadu” station. We will also carry out work related to the construction of working platforms for the “Młyńskie Roundabout” station and the construction of the new channel of the Sudół Dominikański.
As in previous months, the reconstruction of numerous underground networks will continue.