Work on the construction of a new water main is scheduled to begin April 8. As they will be carried out in the existing roadway, access to properties will be provided by the track substructure that is currently being performed.
After the water mains are repiped, work will begin on the construction of a storm sewer system and the reconstruction of a section of the sanitary sewer system. After that, road works will begin.
In addition, appropriate information and organizational measures will be taken. There will be information for residents of Krzeslawicka Street before the work begins. Access roads will be marked, and the work area will be fenced. The pedestrian thoroughfare along the reconstructed section will be preserved. After the road scope is completed, the roadway will be opened to residents, and work will continue on the track.
We ask for your understanding.