We inform you that from November 4th, diaphragm wall excavation works will begin on Młyńska Street.

Due to the need to maintain the continuity of the technological process, the works will be carried out around the clock and will last:

  • Until the end of January on the section from Rondo Młyńskie to Bohaterów Wietnamu Street
  • In February and March on the section from Bohaterów Wietnamu Street to Miechowity Street and south of Rondo Polsadu

The works will generally be conducted from Sunday evening to Friday afternoon.

A holiday break is planned from December 20th to January 7th.

Diaphragm wall excavation involves noise.

The works will start in the area of Rondo Młyńskie, then one of the machines will move north to the height of Bohaterów Wietnamu Street, and the other machine, after completing the works on Młyńska Street, will move to the initial section of the tunnel (south of Rondo Młyńskie).

We apologize for any inconvenience and disruptions.