2500-Meter Underground Reconstruction Completed

The reconstruction of the heating network as part of the Tram to Mistrzejowice project has been completed. All works were finished before the heating season began to avoid inconveniences for residents.

Gülermak, the company responsible for the Tram to Mistrzejowice project, completed the reconstruction of the heating network from Jana Pawła II Avenue to Rondo Młyńskie and the heating chambers at Bohomolca and Jancarza streets. Since the beginning of the tram line construction to Mistrzejowice, builders have modernized or rebuilt over 2500 meters of underground heating infrastructure.

The reconstruction works were carried out in stages. Due to the pipe welding technology used, each section had to be fully heated before backfilling the trench. Pipe welding is a process of joining pipes by heating their ends until they become plastic and then joining them to create a durable and tight joint. On Meissnera Street, it was necessary to weld two pipe segments with a total length of about 200 meters.

The smallest pipes used in the project had a diameter of just 150 mm, while the largest had a diameter of 1000 mm. These pipes were placed under sidewalks, bike paths, parking lots, and green areas. This arrangement not only facilitates access to the installation during repairs but also minimizes traffic disruptions during maintenance works. In case of repairs, it does not require disturbing the road surface, which minimizes traffic disruptions.

– A major challenge was to carry the pipes through the main street crossings. To minimize traffic disruptions, we created temporary crossings that ensured smooth traffic flow and allowed the continuation of works, – says Paweł Kos, sanitary works manager at Gülermak.

The reconstruction of the heating network was necessary due to conflicts with the diaphragm walls being built at the beginning of Meissnera Street and near Rondo Młyńskie, as well as due to its overlap with the planned tram line route. Additionally, modernization was necessary to adapt the underground networks to current technical standards and to provide residents with access to safe and durable infrastructure.

The works were carried out outside the heating season, which allowed avoiding interruptions in the supply of heat and hot water, – says Magdalena Nowak-Obrzut, Director of the Kraków City Roads Authority. Thanks to the cooperation with the network operator – the Municipal Heat Energy Company (MPEC) and our subcontractors, the works and inspections went smoothly and successfully, – emphasizes Paweł Kos.

Czytaj dalej

Switching of the DN800 Main Line – Hot Water Supply Interruptions

Switching of the DN800 Main Line – Hot Water Supply Interruptions

Due to connection works carried out by the Municipal Heat Energy Company, there will be periodic interruptions in the supply of hot water until September 18, 2024, at 6:00 AM.

This affects buildings located near the following streets:

  • Fiołkowa street
  • Markowskiego street
  • Seniorów Lotnictwa street
  • Spadochroniarzy street
  • Ugorek street
  • Ułanów street
Czytaj dalej

Tram to Mistrzejowice Work Schedule

Due to discrepancies appearing in the public space, we remind you that the schedule of works and their progress is regularly presented on the website and social media, as well as every two weeks during Construction Councils with the participation of representatives of UM Kraków, Councilors, and Residents.

To clear up any doubts, we present the main scope of works and their completion dates:

  • Completion of the reconstruction of the Mistrzejowice Loop in terms of tracks – Q4 2024
  • Execution of the intermediate slab of the Polsad station (level -1) – Q4 2024
  • Completion of the construction of diaphragm walls – Q1 2025
  • Execution of the bottom slab (level -2) of the Polsad station – Q2 2025
  • Completion of tunnel construction works – Q3 2025
  • Tunnel equipment installation – Q4 2025
  • Construction of the tram track – Q4 2025
  • Finishing works (small architecture and plantings) – Q1 2026

The Detailed Work Schedule, understood as part of the Public-Private Partnership Agreement, contains very detailed information on the implementation of the works. This document has been reported as protected by trade secrets due to its high level of detail and significant data regarding the technology of the works.

Since the beginning of the investment, we have answered all, even the most difficult, questions. We are at your disposal:

  • By phone at the project hotline – 722 22 00 88
  • At the information point (Rondo Stanisława Barei)
  • On social media (Facebook)
  • By email at info@tramwajdomistrzejowic.pl
Czytaj dalej

Construction Site Report: August 2024

The construction of the 4.5-kilometer tram line to Mistrzejowice is ongoing, with recent weeks bringing further progress. In the new material, you will see how we use BIM technology in planning and monitoring construction works.

Building Information Modeling (BIM) is a technology used in the construction industry that helps in creating, managing, and analyzing information about buildings or infrastructure in a digital and 3D manner. You can read more about this in one of our articles: BIM Technology.

In the report, you will see how BIM technology affects the progress of the work and what innovative solutions are being implemented on the construction site. The material also presents details of the progress made in August.

We invite you to watch the video and follow the next stages of the construction of the tram line to Mistrzejowice.