Due to discrepancies appearing in the public space, we remind you that the schedule of works and their progress is regularly presented on the website and social media, as well as every two weeks during Construction Councils with the participation of representatives of UM Kraków, Councilors, and Residents.

To clear up any doubts, we present the main scope of works and their completion dates:

  • Completion of the reconstruction of the Mistrzejowice Loop in terms of tracks – Q4 2024
  • Execution of the intermediate slab of the Polsad station (level -1) – Q4 2024
  • Completion of the construction of diaphragm walls – Q1 2025
  • Execution of the bottom slab (level -2) of the Polsad station – Q2 2025
  • Completion of tunnel construction works – Q3 2025
  • Tunnel equipment installation – Q4 2025
  • Construction of the tram track – Q4 2025
  • Finishing works (small architecture and plantings) – Q1 2026

The Detailed Work Schedule, understood as part of the Public-Private Partnership Agreement, contains very detailed information on the implementation of the works. This document has been reported as protected by trade secrets due to its high level of detail and significant data regarding the technology of the works.

Since the beginning of the investment, we have answered all, even the most difficult, questions. We are at your disposal:

  • By phone at the project hotline – 722 22 00 88
  • At the information point (Rondo Stanisława Barei)
  • On social media (Facebook)
  • By email at info@tramwajdomistrzejowic.pl